Pan Mine (Pan Operating Complex) Production Update: $197M NPV
Minera Alamos Inc.'s Pan Mine (Pan Operating Complex) in Nevada, USA has a production guidance outlining a pre-tax NPV of $197M.
Minera Alamos Inc.'s Pan Mine (Pan Operating Complex) has reported production guidance results for the gold project in Nevada, USA. The study headlines a pre-tax net present value of $197M. It reflects Minera Alamos Inc.'s (MAI.V) latest disclosed economics for the asset.
Economics. The pre-tax NPV is $197M.
Production and mine plan. The project envisions an open-pit operation.
Resources and ownership. The company holds a 100% interest in the project.
These figures are extracted from Minera Alamos Inc.'s technical disclosures and reflect the most recent Production Update on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.
Reserves & Resources
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Proven & Probable | — | 0.32 g/t | 222 koz |
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Measured & Indicated | — | 0.33 g/t | 240 koz |
| Heap Leach Inventory | — | — | 33 koz recoverable |
Our Analysis
Its pre-tax NPV is below the company's market capitalisation (roughly 0.5x, on a currency-adjusted basis) — broadly consistent with how the market currently values the company. The project is located in Nevada, USA, a factor in its overall risk profile. For context, gold currently trades around $4,131.50/oz.
Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.