Richmond Hill Gold Project PFS: $2.00B NPV, 70.7% IRR
Dakota Gold Corp.'s Richmond Hill Gold Project in South Dakota, USA (Lead) has a Pre-Feasibility Study (PFS) outlining an after-tax NPV of $2.00B, an after-tax IRR of 70.7%, and initial capital of $538M. The mine plan runs 9 years at about 171 koz Au per year.
Dakota Gold Corp.'s Richmond Hill Gold Project has reported Pre-Feasibility Study (PFS) results for the gold project in South Dakota, USA (Lead). The study headlines an after-tax net present value of $2.00B at a 5% discount rate. It reflects Dakota Gold Corp.'s (DC) latest disclosed economics for the asset.
Economics. The after-tax NPV is $2.00B using a 5% discount rate. After-tax IRR is 70.7%. Initial capital expenditure is estimated at $538M, with life-of-mine sustaining capital of $133M. The study models a payback period of 1.4 years. All-in sustaining costs are pegged at 1289 USD/oz Au. Economics are based on Gold $3,500/oz, silver $50/oz (base case).
Production and mine plan. The project envisions an open-pit operation. Life of mine is 9 years. Average annual production is approximately 171 koz Au. Average head grade is 0.561 g/t Au. Metallurgical recovery averages 72.4%. The open-pit strip ratio is 1.18.
Resources and ownership. Royalties and streams: Various historical royalties totaling effective 2.98% NSR; SD state severance tax; Barrick option to be exercised by Dec 31, 2028.
These figures are extracted from Dakota Gold Corp.'s technical disclosures and reflect the most recent PFS on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.
Reserves & Resources
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Proven | 57,115 kt | 0.613 g/t Au, 7.33 g/t Ag | 1,126 koz Au, 13,457 koz Ag |
| Probable | 62,482 kt | 0.514 g/t Au, 5.96 g/t Ag | 1,033 koz Au, 11,964 koz Ag |
| Proven & Probable | 119,597 kt | 0.561 g/t Au, 6.61 g/t Ag | 2,158 koz Au, 25,421 koz Ag |
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Measured | 8,718 kt | 0.307 g/t Au, 4.03 g/t Ag | 86 koz Au, 1,129 koz Ag |
| Indicated | 28,764 kt | 0.319 g/t Au, 4.36 g/t Ag | 295 koz Au, 4,029 koz Ag |
| Measured & Indicated | 37,482 kt | 0.316 g/t Au, 4.28 g/t Ag | 381 koz Au, 5,158 koz Ag |
| Inferred | 89,731 kt | 0.377 g/t Au, 2.74 g/t Ag | 1,088 koz Au, 8,012 koz Ag |
Our Analysis
- IRR after-tax
- 70.7%
higher than 84% of 133 projects we track
- NPV after-tax
- $2.00B
higher than 82% of 208 projects we track
- Initial capex
- $538M
27% of NPV
costlier than 76% of 193 projects we track
- Payback
- 1.4yrs
slower than 27% of 115 projects we track
- Mine life
- 9yrs
- Discount rate
- 5%
- Study price assumption
- Gold $3,500/oz, silver $50/oz (base case)
- Spot gold today
- $3,633.70/oz
Funding a $538M build is the central question for a company worth US$586M. Initial capex is about 0.9x the entire market cap, so this cannot be paid for out of the balance sheet or a routine placement. The realistic cheques come from three places: a project finance package, a strategic or royalty/streaming partner, or a larger operator buying into the asset or the company. Each has a cost. Debt is available only if the economics hold up at the lender's price deck. A stream or royalty gives away part of the upside. An equity raise of any size, at a company this small, would dilute existing holders heavily. A partner at the asset level is probably the cleanest outcome, but it means selling down a share of the project that the market is currently valuing the company on.
The economics give the company a strong negotiating position. The after-tax IRR of 70.7% sits well above the roughly 15% after-tax level developers typically need to attract project finance, and ranks above 84% of the 133 gold projects we track. After-tax NPV of $2.00B is about 3.4x the market cap, and payback of 1.4 years is faster than 73% of peers. Capex at 27% of NPV is lighter than 24% of the 193 gold projects we track. The study uses $3,500/oz gold against a live spot of $3,633.70/oz, so the base case sits modestly below the market, which leaves some cushion. The wide NPV-to-market-cap gap cuts both ways. It may mean the market has yet to credit the asset, but it may equally reflect skepticism about financing terms, dilution and the distance between a PFS and a build decision.
That distance matters. A PFS narrows the estimate to roughly a plus or minus 25% band, and a build cost already near the company's full equity value leaves little room for overruns. The 9-year mine life is moderate, and South Dakota is a mining-friendly US jurisdiction, which helps lenders and partners. The company's other 5 tracked projects add diversification, but they do not fund this build. The question that decides the outcome is whether management can secure financing at terms that leave existing shareholders with a meaningful share of that $2.00B NPV, rather than handing most of it to whoever writes the cheque.
Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.