Porvenir (Hemco, Nicaragua) PFS: $460M NPV, 37.9% IRR
Mineros S.A.'s Porvenir (Hemco, Nicaragua) in Nicaragua, Región Autónoma de la Costa Caribe Norte has a Pre-Feasibility Study (PFS) outlining an after-tax NPV of $460M, an after-tax IRR of 37.9%, and initial capital of $207M. The mine plan runs 9 years at about 74.7 koz AuEq per year.
Mineros S.A.'s Porvenir (Hemco, Nicaragua) has reported Pre-Feasibility Study (PFS) results for the gold project in Nicaragua, Región Autónoma de la Costa Caribe Norte. The study headlines an after-tax net present value of $460M at a 5% discount rate. It reflects Mineros S.A.'s (MSA.TO) latest disclosed economics for the asset.
Economics. The after-tax NPV is $460M using a 5% discount rate. After-tax IRR is 37.9%. Initial capital expenditure is estimated at $207M. The study models a payback period of 2 years. All-in sustaining costs are pegged at 1295 USD/oz AuEq. Economics are based on US$3,150/oz Au, US$45.00/oz Ag, US$1.22/lb Zn, US$4.72/lb Cu.
Production and mine plan. The project envisions an underground operation. Life of mine is 9 years. Average annual production is approximately 74.7 koz AuEq. Metallurgical recovery averages 88.4%.
Resources and ownership. The company holds a 100% interest in the project.
These figures are extracted from Mineros S.A.'s technical disclosures and reflect the most recent PFS on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.
Reserves & Resources
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Proven & Probable | — | — | 736 Koz AuEq |
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Measured & Indicated | — | — | 233 Koz AuEq |
| Inferred | — | — | 85 Koz AuEq |
Our Analysis
- IRR after-tax
- 37.9%
higher than 51% of 130 projects we track
- NPV after-tax
- $460M
higher than 42% of 204 projects we track
- Initial capex
- $207M
45% of NPV
costlier than 47% of 191 projects we track
- Payback
- 2yrs
slower than 49% of 113 projects we track
- Mine life
- 9yrs
- Discount rate
- 5%
- Study price assumption
- US$3,150/oz Au, US$45.00/oz Ag, US$1.22/lb Zn, US$4.72/lb Cu
- Spot gold today
- $3,863.50/oz
Nicaragua's Costa Caribe Norte is where this gold asset sits, and that matters before any ranking does. It is a higher-risk jurisdiction, so the numbers deserve a wider margin of safety than the same figures would earn in a mining-friendly district. On the peer screen, nothing stands out: the 37.9% after-tax IRR ranks higher than 51% of the 130 gold projects we track, barely into the upper half, while the $460M after-tax NPV beats only 42% of 204. Payback of 2 years is moderate, lower than 51% of 113. For an investor, that means a respectable project rather than a standout one. The IRR is well above the roughly 15% after-tax level developers typically need to attract project finance, so returns are not the obstacle. But a median-ish rank in a jurisdiction that carries a discount is not a reason to pay up.
The constraint that matters most is funding, and here the picture is better than usual. Initial capex of $207M is about 0.1x the company's US$1.69B market cap, and it is one of 17 projects we track for a diversified portfolio. The build is small relative to the equity, so it could plausibly be financed without a transformative raise or a single-asset gamble. Capex is also lower than 53% of the 191 gold projects we track, so the cost of entry is unremarkable in a good way. The NPV at about 0.3x market cap cuts both ways: it may mean the market assigns little value to a 9-year mine in Nicaragua, or that it is skeptical of the jurisdiction and of a development-stage asset that has to compete for capital inside a 17-project portfolio.
Two caveats on the inputs. The study is a PFS, with an accuracy band of roughly plus or minus 25%, so it is not a build decision. The study uses US$3,150/oz gold against live spot of $3,863.50/oz, which leaves room for upside if current prices hold, though the silver, zinc and copper assumptions also contribute to the economics. The question that decides this project is whether Nicaraguan permitting and fiscal terms allow a modest, fundable build to reach production as modeled.
Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.
Get the next one first
Every mining project we track, with its study figures and sources, kept up to date. Sign up and download the data right away.
By signing up, you agree to receive marketing emails from Mining Stocks and to our data license. You can unsubscribe at any time. Privacy policy