Madsen + Rowan Integrated Operation PFS: C$764M NPV Over a 10-Year Mine Life

ByMining Stocks Research
Nov 11, 2026
Source:West Red Lake Gold Mines Ltd.
West Red Lake Gold Mines Ltd. logo
Related Company
West Red Lake Gold Mines Ltd.
$WRLG.V
View Company →

West Red Lake Gold Mines Ltd.'s Madsen + Rowan Integrated Operation in Canada, Red Lake, Ontario has a Pre-Feasibility Study (PFS) outlining an after-tax NPV of C$764M. The mine plan runs 10 years at about 108 koz Au (2029-2034 avg) per year.

West Red Lake Gold Mines Ltd.'s Madsen + Rowan Integrated Operation has reported Pre-Feasibility Study (PFS) results for the gold project in Canada, Red Lake, Ontario. The study headlines an after-tax net present value of C$764M at a 5% discount rate. It reflects West Red Lake Gold Mines Ltd.'s (WRLG.V) latest disclosed economics for the asset.

Economics. The after-tax NPV is C$764M using a 5% discount rate. The study models a payback period of 2.2 years. All-in sustaining costs are pegged at 2457 USD/oz. Economics are based on Base case long-term gold US$3,568/oz; LOM average US$3,782/oz; reserves at US$2,500/oz, 1.35 CAD/USD.

Production and mine plan. The project envisions an underground operation. Life of mine is 10 years. Average annual production is approximately 108 koz Au (2029-2034 avg). Average head grade is 6.8 g/t Au. Metallurgical recovery averages 95%.

Resources and ownership. The company holds a 100% interest in the project.

These figures are extracted from West Red Lake Gold Mines Ltd.'s technical disclosures and reflect the most recent PFS on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.

Reserves & Resources

Mineral Reserves (P&P)
CategoryTonnageGradeContained
Probable4,408 kt6.79 g/t Au962 koz
Mineral Resources (M&I&I)
CategoryTonnageGradeContained
Indicated (Madsen)7,779,305 t5.7 g/t Au1,440,277 oz
Inferred (Madsen)1,213,319 t5.8 g/t Au225,803 oz
Indicated (Rowan)798,989 t13.04 g/t Au335,058 oz
Inferred (Rowan)363,602 t15.31 g/t Au179,029 oz
Mining Stocks Research

Our Analysis

NPV after-tax
C$764M

higher than 56% of 199 projects we track

Payback
2.2yrs

slower than 55% of 110 projects we track

Mine life
10yrs
Study price assumption
Base case long-term gold US$3,568/oz; LOM average US$3,782/oz; reserves at US$2,500/oz, 1.35 CAD/USD
Spot gold today
$4,066.70/oz

Red Lake is one of Canada's best-known gold camps, and a PFS there that carries an after-tax NPV of C$764M, roughly 3.3x the equity value of a US$169M micro-cap, should make investors pause before they get excited. The gap has two honest readings. One is that the market has not yet capitalised an asset sitting in a mining-friendly, well-serviced jurisdiction. The other is that the market doubts the company can fund and permit a build of this scale, and is pricing in heavy dilution or a long delay. Both can be partly true, and the study alone cannot settle which dominates.

The returns support interest without demanding it. The NPV ranks higher than 56% of the 199 gold projects we track, which is above the middle but not exceptional. Payback of 2.2 years is moderate, lower than 45% of the 110 gold peers, so this is not a fast-return story that would ease financing on its own. Ontario lowers the jurisdictional discount and makes the numbers easier to trust on permitting and infrastructure, but it does not remove the funding question. The company is diversified across 5 projects we track, which helps at the margin, yet a micro-cap with that spread still has limited balance-sheet capacity for a single large build.

Price assumptions need careful reading. The study uses a base case long-term gold price of US$3,568/oz and a life-of-mine average of US$3,782/oz, with reserves at US$2,500/oz and 1.35 CAD/USD. Live spot is $4,066.70/oz, above both study decks, so there is upside to the stated economics if spot holds. The conservative reserve price also suggests the resource base is not stretched. The caution is that a PFS is only a plus or minus 25% estimate, not a build decision, and capex or cost drift could erode the margin that spot appears to offer. A 10-year mine life is respectable, not long.

The question that decides this project is whether the company can assemble financing on terms that do not hand most of that NPV to new shareholders and lenders. If it can, the 3.3x gap should narrow through re-rating. If it can only fund through deep discounting, the market's skepticism will have been correct.

Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.

Free email updates

Get the next one first

Every mining project we track, with its study figures and sources, kept up to date. Sign up and download the data right away.