Madsen Mine + Rowan Project (Integrated PFS) PFS: C$764M NPV, C$200M Capex
West Red Lake Gold Mines Ltd.'s Madsen Mine + Rowan Project (Integrated PFS) in Canada, Red Lake, Ontario has a Pre-Feasibility Study (PFS) outlining an after-tax NPV of C$764M and initial capital of C$200M. The mine plan runs 10 years at about 108 koz Au (2029–2034 avg) per year.
West Red Lake Gold Mines Ltd.'s Madsen Mine + Rowan Project (Integrated PFS) has reported Pre-Feasibility Study (PFS) results for the gold project in Canada, Red Lake, Ontario. The study headlines an after-tax net present value of C$764M at a 5% discount rate. It reflects West Red Lake Gold Mines Ltd.'s (WRLG.V) latest disclosed economics for the asset.
Economics. The after-tax NPV is C$764M using a 5% discount rate. Initial capital expenditure is estimated at C$200M, with life-of-mine sustaining capital of C$773M. The study models a payback period of 2.2 years. All-in sustaining costs are pegged at 2457 USD/oz. Economics are based on Base case US$3,568/oz long-term gold (LOM average US$3,782/oz); reserves at US$2,500/oz; 1.35 C$/US$.
Production and mine plan. The project envisions an underground operation. Life of mine is 10 years. Average annual production is approximately 108 koz Au (2029–2034 avg). Average head grade is 6.8 g/t Au. Metallurgical recovery averages 95%.
Resources and ownership. The company holds a 100% interest in the project.
These figures are extracted from West Red Lake Gold Mines Ltd.'s technical disclosures and reflect the most recent PFS on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.
Reserves & Resources
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Probable | 4,408 kt | 6.79 g/t Au | 962 koz Au |
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Indicated (Madsen) | 7,779,305 t | 5.7 g/t Au | 1,440,277 oz Au |
| Inferred (Madsen) | 1,213,319 t | 5.8 g/t Au | 225,803 oz Au |
| Indicated (Rowan) | 798,989 t | 13.04 g/t Au | 335,058 oz Au |
| Inferred (Rowan) | 363,602 t | 15.31 g/t Au | 179,029 oz Au |
Our Analysis
- NPV after-tax
- C$764M
higher than 57% of 197 projects we track
- Initial capex
- C$200M
26% of NPV
costlier than 45% of 186 projects we track
- Payback
- 2.2yrs
slower than 54% of 108 projects we track
- Mine life
- 10yrs
- Study price assumption
- Base case US$3,568/oz long-term gold (LOM average US$3,782/oz); reserves at US$2,500/oz; 1.35 C$/US$
- Spot gold today
- $4,074.90/oz
A C$200M build bill against a company worth US$169M is the number that matters here. Capex is about 0.9x the entire market cap, so this cannot be funded from the treasury or by a quiet placement. The realistic cheque writers are a short list: a strategic or mid-tier producer wanting Red Lake exposure, a royalty or streaming house, a project-finance bank syndicate lending against reserves, or some mix of these. Each wants something in return. A stream or royalty gives away future ounces, debt brings covenants and completion tests, and a large equity raise at a micro-cap's valuation dilutes holders heavily. The company has 4 projects in its portfolio, so it could in principle fund this one by selling or partnering another asset, but that is a choice, not a given.
The economics give the company a decent hand to negotiate with. After-tax NPV of C$764M is about 3.3x market cap and ranks higher than 57% of the 197 gold projects we track. Initial capex is 26% of NPV, lower than 55% of the 186 gold projects we track, so the build is not unusually heavy for what it returns. Payback of 2.2 years is moderate (lower than 46% of 108 peers), which is acceptable to lenders but not a reason for them to waive conditions. The large NPV-to-market-cap gap cuts both ways: it may be unrecognised value, or it may be the market discounting exactly the financing and dilution burden described above. A 10-year mine life in Canada's Red Lake camp, a mining-friendly jurisdiction, helps on the credit side.
Two caveats. This is a PFS, with an accuracy band of roughly plus or minus 25%, and not a build decision, so a capex overrun would hit a thinly capitalised company hard. On price, the study uses US$3,568/oz long-term gold (LOM average US$3,782/oz) with reserves at US$2,500/oz, all below the live spot of $4,074.90/oz. That leaves upside if prices hold, and some cushion for lenders, though spot is no guarantee. The deciding question is what the company has to give up, in equity, ounces or other assets, to close the funding, and how much of that C$764M is left for today's shareholders afterward.
Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.