POLYMETALLIC (ZN, PB, CU, AG, AU, PYRITE)PFSPROJECT ECONOMICS

Iberian Belt West Project PFS: $776M NPV, 23.51% IRR

ByMining Stocks Research
Nov 23, 2026
Source:Emerita Resources Corp.
Emerita Resources Corp. logo
Related Company
Emerita Resources Corp.
$EMO.V
View Company →

Emerita Resources Corp.'s Iberian Belt West Project in Huelva Province, Andalusia, Spain has a Pre-Feasibility Study (PFS) outlining an after-tax NPV of $776M, an after-tax IRR of 23.51%, and initial capital of $567M. The proposed mine plan runs 21 years.

Emerita Resources Corp.'s Iberian Belt West Project has reported Pre-Feasibility Study (PFS) results for the polymetallic (zn, pb, cu, ag, au, pyrite) project in Huelva Province, Andalusia, Spain. The study headlines an after-tax net present value of $776M at a 8% discount rate. It reflects Emerita Resources Corp.'s (EMO.V) latest disclosed economics for the asset.

Economics. The after-tax NPV is $776M using a 8% discount rate. After-tax IRR is 23.51%. Initial capital expenditure is estimated at $567M, with life-of-mine sustaining capital of $280M. The study models a payback period of 6.92 years. Economics are based on Resource prices: US$3,415/t Zn, US$2,425/t Pb, US$13,775/t Cu, US$65/oz Ag, US$3,500/oz Au, US$265/t pyrite concentrate.

Production and mine plan. The project envisions an underground (long-hole open stoping) operation. Life of mine is 21 years.

Resources and ownership. The company holds a 100% interest in the project.

These figures are extracted from Emerita Resources Corp.'s technical disclosures and reflect the most recent PFS on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.

Reserves & Resources

Mineral Reserves (P&P)
CategoryTonnageGradeContained
Probable23.4 Mt2.30% Zn, 1.13% Pb, 0.45% Cu, 53 g/t Ag, 1.07 g/t Au, 33.85% S539 kt Zn, 264 kt Pb, 105 kt Cu, 40,109 koz Ag, 807 koz Au, 7,938 kt S
Mineral Resources (M&I&I)
CategoryTonnageGradeContained
Indicated26.1 Mt2.27% Zn, 1.12% Pb, 0.45% Cu, 52 g/t Ag, 1.04 g/t Au, 33.2% S593 kt Zn, 292 kt Pb, 116 kt Cu, 43,525 koz Ag, 871 koz Au, 8,663 kt S
Inferred9.9 Mt2.13% Zn, 1.00% Pb, 0.50% Cu, 36 g/t Ag, 0.50 g/t Au, 22.7% S212 kt Zn, 100 kt Pb, 50 kt Cu, 11,547 koz Ag, 161 koz Au, 2,256 kt S
Mining Stocks Research

Our Analysis

IRR after-tax
23.5%

higher than 30% of 426 projects we track

NPV after-tax
$776M

higher than 55% of 604 projects we track

Initial capex
$567M

73% of NPV

costlier than 63% of 571 projects we track

Payback
6.9yrs

slower than 98% of 347 projects we track

Mine life
21yrs
Discount rate
8%
Study price assumption
Resource prices: US$3,415/t Zn, US$2,425/t Pb, US$13,775/t Cu, US$65/oz Ag, US$3,500/oz Au, US$265/t pyrite concentrate

A US$25M nano-cap facing a $567M build bill cannot fund this itself, and no amount of study polish changes that. The build cost is about 22.8x the company's entire market cap, so the equity story is really a question of who writes the cheque. Realistic candidates are a strategic partner or major miner buying into the asset, a royalty or streaming house, a bank-led project finance syndicate, or an outright sale of the project. Each takes something. A strategic farm-in typically means ceding a large share of the asset, and a debt-heavy structure needs equity alongside it, issued at a market cap this small. Existing holders should expect to own a thinner slice of a bigger pie, or a small piece of someone else's mine.

The economics are what give the company something to sell. After-tax NPV of $776M is about 31.2x market cap, and ranks ahead of 55% of the 604 projects we track. That gap cuts both ways: it may reflect an unpriced asset, or a market that doubts the financing, the dilution required, permitting in a European jurisdiction, and a PFS-level estimate that still carries a plus or minus 25% band. The 23.5% after-tax IRR is more modest than the NPV suggests. It ranks higher than only 30% of 426 peers, and it clears the roughly 15% bar for project finance and the 20%+ typically demanded of a higher-risk junior with little else behind it, but not by a wide margin. A 6.9-year payback, longer than 98% of the 347 projects we track, leaves capital exposed for a long time, which lenders will notice. Capex at 73% of NPV is moderate, and lower than 37% of the 571 projects we track, so the scale problem is the company's size rather than an unusually costly build.

Supporting factors: Spain is a stable, mining-literate jurisdiction in general terms, a 21-year mine life gives a long runway, and the polymetallic mix (zinc, lead, copper, silver, gold, pyrite concentrate) spreads revenue across several price assumptions. That diversification cuts both ways, since the study's price deck, including US$13,775/t copper and US$3,500/oz gold, needs to hold across many metals. The company's 18-project portfolio does not change the funding arithmetic. The deciding question is whether a credible partner will fund the build on terms that leave current shareholders with meaningful value after dilution.

Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.

Free email updates

Get the next one first

Every mining project we track, with its study figures and sources, kept up to date. Sign up and download the data right away.

By signing up, you agree to receive marketing emails from Mining Stocks and to our data license. You can unsubscribe at any time. Privacy policy

View the source filing from
Emerita Resources Corp.
View Source Filing (PDF) →
◆ ◆ ◆