Iberian Belt West (IBW) PFS: $776M NPV, 23.5% IRR
Emerita Resources Corp.'s Iberian Belt West (IBW) in Spain, Huelva Province (Andalusia) has a Pre-Feasibility Study (PFS) outlining an after-tax NPV of $776M, an after-tax IRR of 23.5%, and initial capital of $567M. The proposed mine plan runs 21 years.
Emerita Resources Corp.'s Iberian Belt West (IBW) has reported Pre-Feasibility Study (PFS) results for the zinc-lead-copper-gold-silver-sulphur (pyrite) project in Spain, Huelva Province (Andalusia). The study headlines an after-tax net present value of $776M at a 8% discount rate. It reflects Emerita Resources Corp.'s (EMO.V) latest disclosed economics for the asset.
Economics. The after-tax NPV is $776M using a 8% discount rate. After-tax IRR is 23.5%. Initial capital expenditure is estimated at $567M. The study models a payback period of 1.9 years. Economics are based on US$274/t pyrite concentrate, US$2,980/t zinc, US$11,470/t copper, US$2,050/t lead, US$3,750/oz gold, US$52/oz silver.
Production and mine plan. The project envisions an underground operation. Life of mine is 21 years. Average head grade is 2.30% Zn, 1.13% Pb, 0.45% Cu, 53 g/t Ag, 1.07 g/t Au.
Resources and ownership. The company holds a 100% interest in the project. Royalties and streams: Royalty-free.
These figures are extracted from Emerita Resources Corp.'s technical disclosures and reflect the most recent PFS on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.
Reserves & Resources
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Probable | 23.4 Mt | 2.30% Zn, 1.13% Pb, 0.45% Cu, 53 g/t Ag, 1.07 g/t Au | 807 koz Au, 40.1 Moz Ag, 539 kt Zn, 264 kt Pb, 105 kt Cu |
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Indicated | 26.1 Mt | 2.27% Zn, 1.12% Pb, 0.45% Cu, 52 g/t Ag, 1.04 g/t Au | 871 koz Au, 43.5 Moz Ag, 593 kt Zn, 292 kt Pb, 116 kt Cu |
| Inferred | 9.9 Mt | 2.13% Zn, 1.00% Pb, 0.50% Cu, 36 g/t Ag, 0.50 g/t Au | — |
Our Analysis
- IRR after-tax
- 23.5%
higher than 30% of 426 projects we track
- NPV after-tax
- $776M
higher than 55% of 604 projects we track
- Initial capex
- $567M
73% of NPV
costlier than 63% of 571 projects we track
- Payback
- 1.9yrs
slower than 26% of 347 projects we track
- Mine life
- 21yrs
- Discount rate
- 8%
- Study price assumption
- US$274/t pyrite concentrate, US$2,980/t zinc, US$11,470/t copper, US$2,050/t lead, US$3,750/oz gold, US$52/oz silver
A US$567M build cost set against a US$25M market cap means this company cannot fund the mine, and no equity raise in the ordinary sense will change that. The build is about 22.8x the company's entire equity value, and the 18-project portfolio is diversified on our tracker but offers no obvious balance-sheet depth to lean on. The realistic cheque writers are few: a strategic partner or major miner taking a project-level stake, a royalty or streaming group, a consortium of lenders backed by export credit or similar support, or an outright sale of the asset. Each of those routes costs existing holders something. A joint venture or sale hands over a large share of the NPV, and any equity needed to unlock debt would be issued at a nano-cap valuation, which is heavily dilutive.
The economics explain why someone might still write it. After-tax NPV of $776M is about 31.2x the market cap, and payback of 1.9 years is fast, quicker than 74% of the projects we track. Capex at 73% of NPV is moderate, and lighter than 37% of the 571 projects in our database. But the IRR of 23.5% ranks in the lower half of our 426-project set, higher than only 30%. It clears the roughly 15% lenders typically want, and just clears the 20%+ expected of a higher-risk junior with little else in the portfolio, but without much margin for a PFS-grade estimate that carries a plus or minus 25% band. A modest capex overrun or weaker metal prices would erode that cushion quickly. The study uses US$3,750/oz gold, US$11,470/t copper and US$2,980/t zinc, so the polymetallic revenue mix is a sensitivity worth watching.
The NPV-to-market-cap gap cuts both ways. It may reflect an unrecognised asset in a 21-year mine life, in Spain, a mining-friendly European jurisdiction with established permitting frameworks. It equally reflects a market that doubts the company can finance the build without surrendering most of the value, and that is wary of a complex pyrite and base-metal flowsheet at pre-feasibility stage. The question that decides the project is whether a partner will fund the build on terms that leave current shareholders with a meaningful retained interest, or whether the equity is diluted or sold away before construction begins.
Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.