Haib Copper Project PFS: $2.54B NPV, 24.9% IRR
Koryx Copper Inc.'s Haib Copper Project in Namibia, Karas Region (southern Namibia) has a Pre-Feasibility Study (PFS) outlining an after-tax NPV of $2.54B, an after-tax IRR of 24.9%, and initial capital of $2.06B. The mine plan runs 24 years at about 105 kt payable Cu (LOM); 130 kt first 10 years per year.
Koryx Copper Inc.'s Haib Copper Project has reported Pre-Feasibility Study (PFS) results for the copper project in Namibia, Karas Region (southern Namibia). The study headlines an after-tax net present value of $2.54B at a 8% discount rate. It reflects Koryx Copper Inc.'s (KRY.V) latest disclosed economics for the asset.
Economics. The after-tax NPV is $2.54B using a 8% discount rate. After-tax IRR is 24.9%. Initial capital expenditure is estimated at $2.06B, with life-of-mine sustaining capital of $639M. The study models a payback period of 3.9 years. All-in sustaining costs are pegged at 2.52 USD/lb Cu (LOM); 2.07 first 10 years. Economics are based on US$5.00/lb Cu (US$11,023/t), US$3,500/oz Au, US$22/lb Mo, flat LOM.
Production and mine plan. The project envisions an open-pit operation. Life of mine is 24 years. Average annual production is approximately 105 kt payable Cu (LOM); 130 kt first 10 years. Average head grade is 0.27% Cu LOM (0.32% first 10 years). Metallurgical recovery averages 87.3%. The open-pit strip ratio is 0.98:1.
Resources and ownership. The company holds a 100% interest in the project. Royalties and streams: 3% government royalty (tax-deductible) and 1% export levy; no streaming or offtake prepayment.
These figures are extracted from Koryx Copper Inc.'s technical disclosures and reflect the most recent PFS on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.
Reserves & Resources
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Indicated | 1,371 Mt | 0.26% Cu, 59 ppm Mo, 0.02 g/t Au | 3,572 kt Cu, 81 kt Mo, 892 koz Au |
| Inferred | 329 Mt | 0.24% Cu, 41 ppm Mo, 0.02 g/t Au | 781 kt Cu, 13 kt Mo, 178 koz Au |
Our Analysis
- IRR after-tax
- 24.9%
higher than 70% of 46 projects we track
- NPV after-tax
- $2.54B
higher than 85% of 53 projects we track
- Initial capex
- $2.06B
81% of NPV
costlier than 66% of 58 projects we track
- Payback
- 3.9yrs
slower than 52% of 42 projects we track
- Mine life
- 24yrs
- Discount rate
- 8%
- Study price assumption
- US$5.00/lb Cu (US$11,023/t), US$3,500/oz Au, US$22/lb Mo, flat LOM
- Spot copper today
- $5.74/lb
A US$2.06B build cost against a US$282M market cap means the company cannot fund this itself, and no ordinary equity raise gets it there. At about 7.3x its entire equity value, the initial capex has to be carried by someone else: a strategic buyer, a major mining partner taking a project-level stake, or a consortium of project lenders, development finance institutions and offtake or streaming providers. For a micro-cap with only three projects on our tracking list, the realistic outcome is a large farm-in, a takeover, or a heavily structured package, not a standalone financing. Existing holders should assume that any route to construction either dilutes them materially or hands control of the asset to a better-capitalised owner.
The economics are what make that conversation possible. After-tax NPV of $2.54B is about 9x the market cap and ranks higher than 85% of the 53 copper projects we track. The 24.9% after-tax IRR ranks higher than 70% of 46 peers and clears the roughly 15% typically needed for project finance. It also clears the 20%+ usually asked of a higher-risk junior with little else in the portfolio, though not by a wide margin. Capex at 81% of NPV is moderate and lower than 34% of tracked copper projects, so the build is not unusually heavy for the sector; it is only heavy for this balance sheet. Payback of 3.9 years is middling. The study price of US$5.00/lb copper sits below the live $5.74/lb, which leaves some upside if spot holds, though the study also leans on gold and molybdenum credits at flat prices over a 24-year life.
The market gap cuts both ways. A 9x NPV-to-market-cap ratio could mean the asset is not yet recognised, but it more likely reflects a discount for funding and dilution risk, a PFS-level estimate carrying a plus or minus 25% band, and the fact that Karas Region in Namibia, a generally mining-friendly jurisdiction, still has to deliver permits and infrastructure for a build this large. A cost overrun at the edge of that band would pressure a thin IRR cushion. The question that decides this is what a financing partner will pay for control of the project, and whether current shareholders keep meaningful exposure to the 9x NPV after that deal is struck.
Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.