Cauchari-Olaroz Feasibility Study: $3.06B NPV, 28.5% IRR

ByMining Stocks Research
Nov 20, 2026
Source:Lithium Argentina Corp.
Lithium Argentina Corp. logo
Related Company
Lithium Argentina Corp.
$LAR.TO
View Company →

Lithium Argentina Corp.'s Cauchari-Olaroz in Argentina (Cauchari and Olaroz Salars, Jujuy) has a Feasibility Study outlining an after-tax NPV of $3.06B, an after-tax IRR of 28.5%, and initial capital of $1.01B. The mine plan runs 40 years at about 45000 t LCE (expansion project) per year.

Lithium Argentina Corp.'s Cauchari-Olaroz has reported Feasibility Study results for the lithium project in Argentina (Cauchari and Olaroz Salars, Jujuy). The study headlines an after-tax net present value of $3.06B at a 8% discount rate. It reflects Lithium Argentina Corp.'s (LAR.TO) latest disclosed economics for the asset.

Economics. The after-tax NPV is $3.06B using a 8% discount rate. After-tax IRR is 28.5%. Initial capital expenditure is estimated at $1.01B. The study models a payback period of 3 years. Economics are based on Lithium carbonate US$18,000/t.

Production and mine plan. The project envisions a brine extraction wellfield operation. Life of mine is 40 years. Average annual production is approximately 45000 t LCE (expansion project). Average head grade is 580 mg/L Li (reserve average). Metallurgical recovery averages 63%.

Resources and ownership. The company holds a 44.8% interest in the project.

These figures are extracted from Lithium Argentina Corp.'s technical disclosures and reflect the most recent Feasibility Study on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.

Reserves & Resources

Mineral Reserves (P&P)
CategoryTonnageGradeContained
Proven227,782,565 m3 brine588.26 mg/L Li75,315 t Li; 400,886 t LCE
Probable526,320,091 m3 brine572.18 mg/L Li190,463 t Li; 1,013,796 t LCE
Proven & Probable754,102,655 m3 brine580 mg/L Li265,779 t Li; 1,414,682 t LCE
Mineral Resources (M&I&I)
CategoryTonnageGradeContained
Measured—557 mg/L Li3,164,540 t Li; 16,844,844 t LCE
Indicated—571 mg/L Li2,122,708 t Li; 11,299,172 t LCE
Measured & Indicated—562 mg/L Li5,287,247 t Li; 28,144,016 t LCE
Inferred—567 mg/L Li1,806,125 t Li; 9,614,004 t LCE
Mining Stocks Research

Our Analysis

IRR after-tax
28.5%

higher than 68% of 25 projects we track

NPV after-tax
$3.06B

higher than 50% of 28 projects we track

Initial capex
$1.01B

33% of NPV

costlier than 48% of 27 projects we track

Payback
3yrs

slower than 26% of 19 projects we track

Mine life
40yrs
Discount rate
8%
Study price assumption
Lithium carbonate US$18,000/t

A US$1.01B build bill against a US$555M market cap means this cannot be funded from the company's own equity without something giving. Existing holders should assume that one of three things happens: a strategic partner or offtaker funds a large share in exchange for a stake in the asset, project-level debt carries most of the load, or the company issues new equity on a scale that reshapes the register. The first is the most realistic route in lithium, where end users and larger producers have repeatedly bought into brine assets, but it usually costs the junior part of the upside through a joint venture interest or a discounted entry. Debt is plausible, though lenders will want offtake cover and a sponsor with a balance sheet, and the equity gap left over still sits against a small-cap.

The economics give financiers something to work with. A 28.5% after-tax IRR clears the roughly 15% level developers typically need to attract project finance by a wide margin, and it ranks above 68% of the 25 lithium projects we track. The after-tax NPV of $3.06B is about 5.5x the company's market cap, but that gap cuts both ways. It may reflect an asset the market has not yet credited, or it may reflect a market discounting the dilution, the financing terms and the jurisdiction. Argentina offers real resource endowment and an established brine district in Jujuy, but it carries higher country risk than the established mining jurisdictions, and investors should read the numbers with that in mind. Note that NPV only ranks around the middle of 28 peers, so the size of the prize is not unusual; the leverage to this company's small equity base is.

Confidence in the inputs is reasonably good. This is a feasibility study, so the figures carry a tighter band than a scoping-level estimate, and the 40-year mine life and 3-year payback help the financing case. The study assumes lithium carbonate at US$18,000/t, and returns should be treated as sensitive to that deck. Capex at 33% of NPV is lighter than for most peers, which helps, but it does not change the funding arithmetic against the market cap. The deciding question is who funds the build, and at what share of the asset: if the capital arrives through a partner at a fair valuation of the project, holders keep meaningful exposure to a high-return asset; if it arrives through heavy discounted equity, much of the NPV transfers to the new capital.

Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.

Free email updates

Get the next one first

Every mining project we track, with its study figures and sources, kept up to date. Sign up and download the data right away.

By signing up, you agree to receive marketing emails from Mining Stocks and to our data license. You can unsubscribe at any time. Privacy policy

View the source filing from
Lithium Argentina Corp.
View Source Filing (PDF) →
◆ ◆ ◆