Cauchari-Olaroz (Expansion Project) PFS: $3.06B NPV, 28.5% IRR
Lithium Argentina Corp.'s Cauchari-Olaroz (Expansion Project) in Argentina (Jujuy), Cauchari and Olaroz Salars has a Pre-Feasibility Study (PFS) outlining an after-tax NPV of $3.06B, an after-tax IRR of 28.5%, and initial capital of $1.01B. The mine plan runs 40 years at about 45 kt LCE per year.
Lithium Argentina Corp.'s Cauchari-Olaroz (Expansion Project) has reported Pre-Feasibility Study (PFS) results for the lithium project in Argentina (Jujuy), Cauchari and Olaroz Salars. The study headlines an after-tax net present value of $3.06B at a 8% discount rate. It reflects Lithium Argentina Corp.'s (LAR.TO) latest disclosed economics for the asset.
Economics. The after-tax NPV is $3.06B using a 8% discount rate. After-tax IRR is 28.5%. Initial capital expenditure is estimated at $1.01B. The study models a payback period of 3 years. Economics are based on US$18,000/t lithium carbonate.
Production and mine plan. The project envisions a brine wellfield pumping with evaporation ponds/dle operation. Life of mine is 40 years. Average annual production is approximately 45 kt LCE. Average head grade is 580 mg/L Li (reserve average). Metallurgical recovery averages 75%.
Resources and ownership. The company holds a 44.8% interest in the project.
These figures are extracted from Lithium Argentina Corp.'s technical disclosures and reflect the most recent PFS on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.
Reserves & Resources
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Proven | 227,782,565 m3 brine | 588.26 mg/L Li | 75,315 t Li; 400,886 t LCE |
| Probable | 526,320,091 m3 brine | 572.18 mg/L Li | 190,463 t Li; 1,013,796 t LCE |
| Proven & Probable | 754,102,655 m3 brine | 580 mg/L Li | 265,779 t Li; 1,414,682 t LCE |
| Category | Tonnage | Grade | Contained |
|---|---|---|---|
| Measured | 5.89E+09 m3 drainable brine | 557 mg/L Li | 2,742,686 t Li; 14,599,317 t LCE |
| Indicated | 3.82E+09 m3 drainable brine | 571 mg/L Li | 2,122,708 t Li; 11,299,172 t LCE |
| Measured & Indicated | 9.71E+09 m3 drainable brine | 562 mg/L Li | 4,865,393 t Li; 25,898,489 t LCE |
| Inferred | 3.24E+09 m3 drainable brine | 567 mg/L Li | 1,806,125 t Li; 9,614,004 t LCE |
Our Analysis
- IRR after-tax
- 28.5%
higher than 68% of 25 projects we track
- NPV after-tax
- $3.06B
higher than 50% of 28 projects we track
- Initial capex
- $1.01B
33% of NPV
costlier than 48% of 27 projects we track
- Payback
- 3yrs
slower than 26% of 19 projects we track
- Mine life
- 40yrs
- Discount rate
- 8%
- Study price assumption
- US$18,000/t lithium carbonate
Funding a US$1.01B build with a US$555M market cap is the first problem to solve, and it is a bigger one than the study's returns. Initial capex is about 1.8x the company's entire equity value, so the cheque cannot come from the balance sheet or from a routine equity raise. Realistic sources are a strategic partner or offtaker taking a project-level stake, a larger producer in the district, or a project finance package from banks and export credit agencies. Each of these costs existing holders something: a minority interest sold at the asset level, a heavily discounted raise, or a covenant-laden debt stack. With only 2 projects tracked for this company, there is little else in the portfolio to cushion that trade.
The economics give the company real bargaining power. The after-tax NPV of $3.06B is about 5.5x market cap, and the 28.5% after-tax IRR sits well above the roughly 15% developers need to attract project finance. It also ranks higher than 68% of the 25 lithium peers we track. Capex is 33% of NPV, lower than 52% of the 27 lithium projects tracked, so the build is not heavy relative to the value it creates. The NPV gap cuts both ways. It may mean the market has not priced the asset. It may equally mean the market is discounting the dilution and execution needed to get it built. A 3-year payback is moderate, and lenders would judge it on the study's US$18,000/t lithium carbonate assumption, so that price is the key sensitivity.
A 40-year mine life supports the case for outside capital, since long-dated cash flows suit project finance and strategic investors who want durable supply. Argentina (Jujuy), in the Cauchari and Olaroz Salars, is an established lithium address, though it carries the jurisdictional risk any lender will price. The PFS stage matters too: it narrows the estimate to roughly a plus or minus 25% band but is not a build decision, so the $1.01B could move. The question that decides this is on what terms the company can secure funding. If a partner buys in near the project's intrinsic value, holders keep most of the upside. If the company has to raise equity near current valuation to bridge the gap, much of that NPV goes to the new money.
Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.