GOLDPEAPROJECT ECONOMICS

Boumadine PEA: $3.50B NPV, 93% IRR

ByMining Stocks Research
Nov 14, 2026
Source:Aya Gold & Silver Inc.
Aya Gold & Silver Inc. logo
Related Company
Aya Gold & Silver Inc.
$AYA.TO
View Company →

Aya Gold & Silver Inc.'s Boumadine in Morocco has a Preliminary Economic Assessment (PEA) outlining an after-tax NPV of $3.50B, an after-tax IRR of 93%, and initial capital of $463M. The mine plan runs 14 years at about 271 koz AuEq per year.

Aya Gold & Silver Inc.'s Boumadine has reported Preliminary Economic Assessment (PEA) results for the gold project in Morocco. The study headlines an after-tax net present value of $3.50B at a 5% discount rate. It reflects Aya Gold & Silver Inc.'s (AYA.TO) latest disclosed economics for the asset.

Economics. The after-tax NPV is $3.50B using a 5% discount rate. After-tax IRR is 93%. Initial capital expenditure is estimated at $463M, with life-of-mine sustaining capital of $507M. The study models a payback period of 0.7 years. All-in sustaining costs are pegged at 1300 USD/oz AuEq. Economics are based on $3,500/oz Au, $50/oz Ag, US$1.37/lb Zn, US$0.90/lb Pb.

Production and mine plan. The project envisions an open-pit & underground operation. Life of mine is 14 years. Average annual production is approximately 271 koz AuEq. Average head grade is 3.10 g/t AuEq LOM (4.11 g/t AuEq Y1-5).

Resources and ownership. The company holds a 85% interest in the project.

These figures are extracted from Aya Gold & Silver Inc.'s technical disclosures and reflect the most recent PEA on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.

Reserves & Resources

Mineral Resources (M&I&I)
CategoryTonnageGradeContained
Indicated8,582 kt121.7 g/t Ag, 1.9 g/t Au, 0.09% Cu, 1.01% Pb, 2.19% Zn, 4.0 g/t AuEq1,110 koz AuEq
Inferred45,365 kt56.8 g/t Ag, 1.8 g/t Au, 0.08% Cu, 0.58% Pb, 1.33% Zn, 2.9 g/t AuEq4,260 koz AuEq
Mining Stocks Research

Our Analysis

IRR after-tax
93%

higher than 92% of 132 projects we track

NPV after-tax
$3.50B

higher than 97% of 206 projects we track

Initial capex
$463M

13% of NPV

costlier than 74% of 192 projects we track

Payback
0.7yrs

slower than 4% of 114 projects we track

Mine life
14yrs
Discount rate
5%
Study price assumption
$3,500/oz Au, $50/oz Ag, US$1.37/lb Zn, US$0.90/lb Pb
Spot gold today
$3,783.30/oz

Morocco's gold development pipeline rarely produces numbers like these: a 93% after-tax IRR, a payback of 0.7 years and an after-tax NPV of $3.50B, all on an initial build of $463M. The IRR ranks above 92% of the 132 gold projects we track, and the NPV sits above 97% of 206. Capex is lower than only 26% of 192 peers, so the build is not unusually cheap in absolute terms. The outlier is the return per dollar spent. Against the roughly 15% after-tax IRR developers typically need to attract project finance, this clears the bar by a very wide margin.

That gap is the reason to be skeptical. A scoping-level PEA is preliminary, may lean on inferred resources, and its capital estimate typically carries a plus or minus 50% band. Even a badly overrun build would probably still screen well, but the more important exposure is upstream of capex: grade, recovery and the polymetallic inputs. The deck includes silver, zinc and lead credits, so the economics depend on a basket rather than gold alone, and a 14-year mine life is respectable rather than long. The gold price assumption of $3,500/oz sits below the live spot of $3,783.30/oz, which gives some cushion on the gold side, though the by-product prices are not covered by that comparison. Morocco is generally a mining-friendly, established jurisdiction, which supports reading the numbers at face value on fiscal terms, but a PEA's tax and royalty treatment still deserves checking against the final permitting position.

On funding, the picture is unusually benign. The build cost is about 0.1x the company's US$3.24B market cap, so this is a mid-cap with four tracked projects, not a developer betting its equity on one asset. It can plausibly fund the build from cash flow, debt or a modest raise. The NPV at about 1.1x market cap cuts both ways: the market may be underweighting a project that has not yet been de-risked, or it may be discounting a PEA-grade study for exactly the reasons above. The question that decides this is whether feasibility-level work confirms the grade, recovery and capex that produce the returns. If it does, this is a rare asset. If the headline economics erode materially, the market's skepticism will have been justified.

Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.

Free email updates

Get the next one first

Every mining project we track, with its study figures and sources, kept up to date. Sign up and download the data right away.

By signing up, you agree to receive marketing emails from Mining Stocks and to our data license. You can unsubscribe at any time. Privacy policy

View the source filing from
Aya Gold & Silver Inc.
View Source Filing (PDF) →
◆ ◆ ◆