Gold$2,045.30+0.52%
Silver$23.84-0.18%
Copper$3.85+1.23%
Platinum$912.40-0.33%
Iron Ore$118.50+2.14%
Nickel$16,892-0.89%
Consolidated Lithium Metals Inc. logo

Consolidated Lithium Metals Inc.

CLM.VSmall CapLithium

Price History

Loading chart...

About Consolidated Lithium Metals Inc.

Consolidated Lithium Metals Inc. (CLM.V) is a lithium mining company listed on the TSX Venture Exchange (TSXV). Our project database tracks 3 projects for Consolidated Lithium Metals Inc. with technical and economic data extracted from company filings. Its flagship Kwyjibo Project (Josette Zone) (PEA) carries an after-tax NPV of C$1.40B and an IRR of 35.4% over a 10-year mine life.

Consolidated Lithium Metals focuses on acquiring and exploring prospective lithium pegmatite and brine properties across North America. The company pursues assets with exploration upside and development potential.

Primary Commodities

Lithium

Project Economics

Kwyjibo Project

Rare Earth Elements· Côte-Nord administrative region, Quebec, Canada (approx. 125 km northeast of Sept-Îles)· Development
PEA
Oct 2026
Initial CapexC$889M
Annual Production10,053 t TREO
Recovery75%
Mine TypeUnderground (long hole, longitudinal and transverse)
Ownership80%
Mineral Resources
Combined Measured & Indicated: 8,480 kt @ 2.45% TREO; Inferred: 1,825 kt @ 3.26% TREO (Josette Zone)

Kwyjibo Project (Josette Zone)

Rare Earth Elements (TREO)· Quebec, Canada (Côte-Nord region, ~125 km northeast of Sept-Îles)· Development
PEA
Aug 2026
NPV (After-Tax) @ 8%C$1.40B
NPV (Pre-Tax)C$2.40B
IRR (After-Tax)35.4%
Initial CapexC$881M
Payback2 yrs
Mine Life10 yrs
Annual Production9.8 kt TREO
Head Grade3.35% TREO (average over LOM)
Recovery75%
Mine TypeUnderground (long hole, longitudinal and transverse)
Mineral Resources
Combined (Josette Zone): Measured 3,138 kt @ 2.37% TREO; Indicated (Shown) 5,342 kt @ 2.49% TREO; M+I 8,480 kt @ 2.45% TREO; Inferred 1,825 kt @ 3.26% TREO. Effective date 25 June 2026.

Kwyjibo Rare Earth Project

Rare Earth Elements (TREO)· Quebec, Canada (Côte-Nord / Sheldrake)· Development
PEA
Jun 2026
NPV (After-Tax) @ 8%C$1.40B
NPV (Pre-Tax)C$2.40B
IRR (After-Tax)35.4%
Initial CapexC$881M
Payback2 yrs
Mine Life10 yrs
Annual Production9.8 kt/y TREO
Head Grade3.35% TREO (LOM average)
Recovery75%
Mine TypeUnderground
Mineral Resources
Combined Josette zones: M&I 8,480 kt @ 2.44% TREO; Inferred 1,825 kt @ 3.27% TREO

Project figures are automatically extracted from company filings and presentations and reflect the most recent disclosure found. They may contain errors — always verify against the linked source document.

Free email updates

Find the best mining projects

Be the first to know about new mining results, and how they compare to other projects.

Financial Metrics

Loading financial data...

Frequently Asked Questions

What does Consolidated Lithium Metals Inc. mine?
Consolidated Lithium Metals Inc. is focused on Lithium.
What is the economic value of Consolidated Lithium Metals Inc.'s Kwyjibo Project (Josette Zone)?
According to its PEA, Kwyjibo Project (Josette Zone) has an after-tax NPV of C$1.40B and an IRR of 35.4%.
What exchange is Consolidated Lithium Metals Inc. listed on?
Consolidated Lithium Metals Inc. trades under the ticker CLM.V on the TSX Venture Exchange (TSXV).
How many projects does Consolidated Lithium Metals Inc. have?
We track 3 projects with extracted technical and economic data for Consolidated Lithium Metals Inc.

Project Analysis

Quick Facts

Ticker Symbol
CLM.V
Market Cap
Small Cap
Category
Lithium
Commodities
Lithium

This information is for educational purposes only and does not constitute investment advice. Always conduct your own research before making investment decisions.

◆ ◆ ◆