COPPERFEASIBILITY STUDYPROJECT ECONOMICS

Yellowhead Project Feasibility Study: C$2.00B NPV, C$2.00B Capex

ByMining Stocks Research
Oct 9, 2026
Source:Taseko Mines Limited
Trekor Metals Limited logo
Related Company
Trekor Metals Limited
$TGB
View Company →

Taseko Mines Limited's Yellowhead Project in Thompson-Nicola, British Columbia, Canada (150 km NE of Kamloops) has a Feasibility Study outlining an after-tax NPV of C$2.00B and initial capital of C$2.00B. The mine plan runs 25 years at about 178 Mlb Cu per year.

Taseko Mines Limited's Yellowhead Project has reported Feasibility Study results for the copper project in Thompson-Nicola, British Columbia, Canada (150 km NE of Kamloops). The study headlines an after-tax net present value of C$2.00B at a 8% discount rate. It reflects Taseko Mines Limited's (TGB) latest disclosed economics for the asset.

Economics. The after-tax NPV is C$2.00B using a 8% discount rate. Initial capital expenditure is estimated at C$2.00B. Economics are based on US$4.25/lb copper base case (after-tax NPV8 C$2.0 billion); at long-term consensus US$5.25/lb copper after-tax NPV8 is C$3.6 billion.

Production and mine plan. The project envisions an open-pit operation. Life of mine is 25 years. Average annual production is approximately 178 Mlb Cu. The open-pit strip ratio is 1.4:1.

Resources and ownership. The company holds a 100% interest in the project.

These figures are extracted from Taseko Mines Limited's technical disclosures and reflect the most recent Feasibility Study on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.

Mining Stocks Research

Our Analysis

NPV after-tax
C$2.00B

higher than 74% of 43 projects we track

Initial capex
C$2.00B

100% of NPV

costlier than 66% of 47 projects we track

Mine life
25yrs
Study price assumption
US$4.25/lb copper base case (after-tax NPV8 C$2.0 billion); at long-term consensus US$5.25/lb copper after-tax NPV8 is C$3.6 billion
Spot copper today
$6.61/lb

A C$2.00B after-tax NPV puts this project ahead of roughly three-quarters of the 43 copper projects we track, and the capex sits below only a third of the 47 we benchmark. That combination (upper-tier value against mid-pack build cost) is a respectable place to sit, but it is not a standout. The more useful observation is the flat line against the previous filing: NPV, capex and mine life all unchanged at +0%. A feasibility study that re-confirms its predecessor tells you the estimate is stable and de-risked, not that anything has improved. The ±15% band of an FS is the reason to take these numbers seriously; it is also the reason a zero-delta update reads as consolidation rather than progress.

The constraint that decides this one is funding, not geology. Initial capex of C$2.00B equals the entire after-tax NPV and lands at roughly half the company's US$2.91B market cap. A build of that size relative to equity cannot be financed quietly: it implies either a large debt and offtake package, a partner, or meaningful dilution, and the market will price that overhang long before first pour. The diversified five-project portfolio softens the single-asset risk but also means this build competes for capital against four other calls on the same balance sheet.

British Columbia is a mining-friendly jurisdiction with a permitting path investors can underwrite, which is a genuine quality signal, though timelines there are measured in years. The study's US$4.25/lb base case sits well below today's $6.61/lb spot, and at US$5.25/lb consensus the NPV rises to C$3.6B, so there is real leverage to price, but the base case is the number to finance against. The question that settles it: can this company carry a C$2.00B build at half its market cap without diluting the equity case away?

Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.

Free email updates

Get the next one first

Every mining project we track, with its study figures and sources, kept up to date. Sign up and download the data right away.

By signing up, you agree to receive marketing emails from Mining Stocks and to our data license. You can unsubscribe at any time. Privacy policy

View the source filing from
Taseko Mines Limited
View Source Filing (PDF) →
◆ ◆ ◆