ANTIMONYRESOURCE ESTIMATEPROJECT ECONOMICS

Limousine Butte - Project Jumpstart Antimony (Phase 1, Leach Pads) Resource Estimate: $50M Capex

ByMining Stocks Research
Nov 1, 2026
Source:NevGold Corp.
NevGold Corp. logo
Related Company
NevGold Corp.
$NAU.V
View Company →

NevGold Corp.'s Limousine Butte - Project Jumpstart Antimony (Phase 1, Leach Pads) in Nevada, USA has a Mineral Resource Estimate outlining initial capital of $50M.

NevGold Corp.'s Limousine Butte - Project Jumpstart Antimony (Phase 1, Leach Pads) has reported Mineral Resource Estimate results for the antimony project in Nevada, USA. It reflects NevGold Corp.'s (NAU.V) latest disclosed economics for the asset.

Economics. Initial capital expenditure is estimated at $50M.

Production and mine plan. The project envisions a re-processing of leach pads (no mining) operation. Average head grade is 0.28% Sb (M&I).

Resources and ownership. The company holds a 100% interest in the project.

These figures are extracted from NevGold Corp.'s technical disclosures and reflect the most recent Resource Estimate on file. Compare this project against other developers and producers in our project economics database, and always verify the numbers against the original technical report before making any investment decision.

Reserves & Resources

Mineral Resources (M&I&I)
CategoryTonnageGradeContained
Total Measured & Indicated2.3 Mt0.28% Sb6,900 t Sb
Inferred0.05 Mt0.99% Sb500 t Sb
Mining Stocks Research

Our Analysis

Initial capex
$50M

costlier than 16% of 546 projects we track

A US$50M build against a US$66M market capitalisation is the fact that governs this asset. The company cannot fund that from its own balance sheet, and at roughly 0.8x its entire equity value the cheque is large enough that whoever writes it will want a meaningful slice of the company in return. That points to the usual paths: a partner or offtaker carrying a share of construction, project-level debt against a resource that has no reserve statement behind it, or equity issued at micro-cap prices. Each of those transfers value away from current holders, and the last is the most punitive.

The economics themselves are thinner ground than they look. This is a resource estimate, not a feasibility study, so there is no economic study underpinning the numbers, and any returns quoted are indicative at best. Antimony adds a second layer of uncertainty: pricing is opaque and the study's own assumption should be read as a sensitivity rather than a forecast, because there is no reliable live reference to test it against. A project of this size can look workable on paper and still fail at the financing table.

Nevada is the genuine positive. A US jurisdiction with an established permitting and mining framework lowers the political and execution risk that would otherwise compound the funding question, and it widens the pool of lenders and partners who will engage at all. But it does not change the arithmetic: the company is one of 10 projects in a diversified micro-cap portfolio, which raises the question of how much of the group's limited capital and management attention this build can actually command.

The single question is whether a partner or lender can be brought in on terms that fund US$50M without handing control of the asset, and most of the equity value, to someone else.

Our take, benchmarked against the project economics in the Mining Stocks database. Figures are estimates drawn from company technical reports — not investment advice; always verify against the source filing.

Free email updates

Get the next one first

Be the first to know about new mining results, and how they compare to other projects.

View the source filing from
NevGold Corp.
View Source Filing (PDF) →
◆ ◆ ◆